In 2026 I worked as an analyst on an ATS (applicant tracking system) project. Ideas kept coming, and at one point we had more than 20 epics in progress at the same time. I could not keep them in my head. I could not even keep a list of them in my head.
What helped was a simple board of epics. This kind of board has a name: Portfolio Kanban. The Agile Extension to the BABOK Guide v2 describes it as technique 7.9 and places it at the Strategy Horizon [1].
Below is what this board gave me, what practitioners do with it at a larger scale, and what to remember for the AAC exam.
What the Agile Extension says
Portfolio Kanban is a Kanban board one level up. Cards are initiatives or epics, not tasks. The board shows how many big pieces of work run at the same time.
The Agile Extension v2 (IIBA and Agile Alliance, 2017) lists it in Chapter 7 as section 7.9, between Planning Workshops and Product Roadmap [1]. In the Strategy Horizon section, the guide describes it as a way to see the progress of initiatives across the portfolio in real time. The same section says it can be combined with a Balanced Scorecard or a Value Stream Map to decide where to put resources [1].
So the guide treats it as a strategy tool, not a delivery tool. It answers what we work on and how much of it at once. How the teams build each item is a different level.
My first board: five epics and a Confluence page
The first time was in 2021–2022. I worked as an analyst on a data analytics project for an MBB consulting firm. All the work was about one product, with up to five or six epics in progress at any moment.
The board was simple. Three standard columns, with our own meaning:
| Column | What it meant for us |
|---|---|
| Backlog | I prepare the epic: analysis, open questions, requirements |
| Doing | Developers build it |
| Testing | Testing |
I kept it as a Confluence page and updated it by hand.
I did not use it to track progress. Jira did that. The board did something else: it reminded me how much we had in work, what came next, and what my debts were. An epic in Backlog was my debt. If I did not finish the analysis, the team could not start.
My second board: more than 20 epics in Linear
On the ATS project the board lived in Linear and had seven columns:
| Column | What it meant |
|---|---|
| Created | The idea is recorded, nobody works on it yet |
| Preparation | I am analysing it |
| Ready for work | Analysis is done, the team can take it |
| Development | Developers build it |
| Testing | Testing |
| To deploy | Tested, waiting for release |
| Done | Released |
The most useful part was the split between "Preparation" and "Ready for work". I could see at once which epics were still my debt and which were already waiting for the team.
What I took from both cases
Two projects, two very different loads. And the same conclusion: the main value of the board for me was not control, but memory.
Five or six epics are already too many to keep in your head together with their open questions. More than 20, with a stream of new ideas, is impossible. So for an analyst the board is, first of all, external memory.
What I would change in the first board today:
- One more column. Backlog mixed two states: "planned, nobody touches it" and "I am analysing it now". I would split them, the way the ATS board did. Practitioners recommend the same: show the analysis stage and the queue after it separately, so the waiting is visible [3][4].
- A Jira filter instead of a manual page. A Confluence page goes stale the moment you forget to update it. A board built from a filter updates itself. Atlassian once solved the same problem with a rule: the owner of each investment updates its status every Friday by noon [24]. A filter makes such a rule unnecessary.
And one thing I would do first: agree on the board with the stakeholders, its form and who keeps it. It is quite possible that a project does not need it at all. For one product and five epics, a separate portfolio board can become one more artifact nobody opens.
Let's look at it through a different lens
My boards were tools for one analyst. At company level the same board does a different job: it limits how many initiatives an organisation starts. I collected the main practices from practitioner guides and reports.
1. Limit the number of initiatives in progress
Fewer things started means more things finished. The hard part is choosing the limit, because initiatives differ in size. The methods people use:
| Method | Source |
|---|---|
| Number of teams: 6 teams can hardly move more than 6–9 initiatives | ProKanban playbook [7], Rally guide [26] |
| Halve the current WIP | ProKanban playbook [7] |
| Start with a best guess, watch for 4–6 weeks, then adjust | ProKanban playbook [7] |
| Headcount of a business area ÷ 5 | Trade Me [14] |
| Total staff ÷ 7 if teams are not stable | Rally guide [26] |
| Number of available Epic Owners, for the analysis stage | SAFe guides [6] |
| No fixed number: reduce WIP and decide each new start in a conversation | Pawel Brodzinski [10], Yuval Yeret [16] |
The last row is the most interesting. Brodzinski noticed back in 2012 that limiting the number of projects rarely works, because their sizes differ too much [9]. Later he wrote that a 1:200 ratio between the smallest and the largest project is common [10]. Yeret goes further: with initiatives from 5 to 500 person-months, a count limit mostly measures leadership attention, not capacity. His advice is to reduce WIP rather than limit it, and to ask which cards do not need to be on the portfolio board at all [16].
2. Separate options from commitments
Most boards have a funnel or "might do" column before the point of commitment. In SAFe, the states are Funnel, Reviewing, Analyzing, Backlog, Implementing and Done; an epic moves past Analyzing only after a go/no-go decision on its business case [4]. An Epic Owner moves each epic through the board [2]. Brian Tucker also suggests a way to stop an epic at any stage, so sunk costs do not keep it alive [3].
3. Order by cost of delay
The backlog of initiatives is often ordered by cost of delay or WSJF [4][6][18]. Cost of delay across a portfolio is also a core topic in David Anderson's Enterprise Services Planning [22]. Trade Me did it differently: a one-page canvas for each project and a prioritisation workshop every 3–6 months [14].
4. Show dependencies across teams
Initiative cards can have child cards on team boards, so status rolls up from team level to portfolio level [18][20][29]. The Modus Cooperandi glossary defines the technique mainly through this cross-team view of dependencies, bottlenecks and capacity [30]. Some tools add capacity checks across projects and a Gantt view for dependencies [28]. Flight Levels describes the same idea: the strategic level breaks strategy into initiatives, and the coordination level connects teams [31].
5. Give decisions a rhythm
A board is useless without a meeting where people decide. Trade Me held its weekly projects team meeting in front of the board [14]. The Rally guide suggests a monthly portfolio council with a biweekly review [26].
The main thesis
Put the two views together, and the picture is simple. Portfolio Kanban does not make decisions; it makes the cost of starting one more initiative visible. For an analyst this cost is a queue of epics waiting for analysis. For a company it is projects that never finish.
The numbers from practice support this:
| Case | Result |
|---|---|
| Trade Me, 2013–2014, 110–125 tech staff [14][15] | Projects in progress fell from 49 to 18; average cycle time from about 250 to about 55 days within a year |
| Investment bank, SAFe Portfolio Kanban, year not stated [5] | Business analysis took over 70% of lead time; with weekly pull, BA lead time fell from about 9 to under 3 months |
| SCHLENK, manufacturer, 1,000+ staff, year not stated [19] | Cycle time from 110 to 44 days (vendor case study) |
| Kanban Leadership Retreat, informal data, reported in 2014 [11] | Average projects per person in different companies: 1.0, 2.1, 4.5 and 6.0 |
The investment bank case is the closest to my own. The bottleneck was not development but the analysis before it [5]. I saw the same on a small scale: an epic waiting for my analysis was the team's waiting time.
Where it goes wrong
- Blocked on the board, not stopped in reality. At Trade Me, putting a "blocked" note on a project was easy; actually stopping people from working on it was much harder [14].
- Count limits that ignore size. One big programme and one small fix take the same slot [9][16][33].
- Too many columns or rules. The ProKanban playbook warns against boards copied with every governance gate as a column [7][8]; the Rally guide says a long exit policy was ignored and advises keeping it short [26].
- The board as a copy of Jira. A ticket list with no WIP limits and no cadence is listed as an anti-pattern [8]. Practitioners also say epics are often too low-level for a portfolio view [25].
- No owner. Trade Me found the board goes out of date without a designated owner and a fixed update rhythm [14]. For Brodzinski, one person keeping the board was enough to see early results [13]. My Confluence page had this risk too.
- Too much on the board. Yeret suggests scoring each card on size, strategic risk and cross-team collaboration, and leaving low-scoring items to product teams [17]. A busy board also hides waiting time between disconnected boards [27].
- Expecting the board to make the strategy. It helps people have the conversation about what to build; it does not decide for them [12]. Mike Burrows argues that a board of initiatives is not enough without the other Kanban practices and leadership agreement [23].
What this means for a business analyst
From the cases above and my own projects, I see four jobs for a BA:
- Prepare initiatives before commitment. The analysis column is often the real queue [5].
- Make your own debt visible. Epics waiting for analysis are blocked work, even if nobody calls them that.
- Point out dependencies between initiatives and teams [18][29].
- Agree the rules of the board with stakeholders: columns, the limit, who updates it and how often.
For the AAC exam
As of October 2026, IIBA says the AAC exam is formulated from the Agile Extension, with competencies aligned to version 2 [34]. So expect scenario questions rather than definitions. Things to keep straight:
- Portfolio Kanban is an Agile Extension technique (7.9) at the Strategy Horizon [1]. It is not one of the 50 BABOK v3 techniques.
- Cards are initiatives or epics, not user stories.
- The purpose is visibility and limiting work in progress across the portfolio, not tracking tasks.
- A typical trap: an answer that uses Portfolio Kanban to manage one team's Sprint work. That is a Delivery Horizon task.
More on the horizons: Agile Extension horizons: strategy vs delivery and mapping agile principles to horizons. Related techniques: value stream mapping and Balanced Scorecard. Exam overview: AAC exam guide. The AAC simulator is not live yet; for IIBA-style scenario practice, try the CBAP simulator.
So: if you have more epics than you can remember, you already need this board. Whether the company needs it is a separate conversation.
FAQ
Is Portfolio Kanban the same as a team Kanban board? No. The mechanics are the same, but cards are initiatives or epics, and the question is how many of them the organisation runs at once.
Which horizon is Portfolio Kanban in? The Agile Extension v2 places it at the Strategy Horizon [1].
Does a small project need it? Not always. With one product and a few epics, a simple view such as a Jira filter may be enough. Agree on it with stakeholders first.
How do I set the first WIP limit? Common starting points are the number of teams or half of the current WIP. Another option is a best guess, watched for 4–6 weeks and then adjusted [7][26]. Some practitioners skip the number and work on reducing WIP instead [16]. Later, the board's own data supports portfolio-level forecasting [21][32].
Sources
- IIBA, Agile Alliance. Agile Extension to the BABOK Guide v2, 2017: section 4.7.1 and technique 7.9.
- Scaled Agile. Portfolio Backlog, updated 2025.
- Brian Tucker. On the Nature of Portfolios – Portfolio Kanban Normal Scenarios.
- Brian Tucker. The Dynamics of Decision Making Within the Portfolio Kanban.
- Thorsten Janning. Applied Enterprise Workflow with the SAFe Portfolio Kanban.
- Morné Wiggins. Portfolio Kanban, Agility at Scale.
- Colleen Johnson. The Portfolio Kanban Playbook, ProKanban.org.
- ProKanban.org. Portfolio Playbook: Anti-patterns.
- Pawel Brodzinski. Portfolio Management with Kanban, Planview blog, 2012.
- Pawel Brodzinski. Portfolio management posts, 2011–2013.
- Pawel Brodzinski. Portfolio Management: Stop Starting, Start Finishing, 2014.
- Pawel Brodzinski. Portfolio Kanban and Doing the Right Thing, 2014.
- Pawel Brodzinski. Portfolio Kanban: Why Should I Care?, 2013.
- Sandy Mamoli. Portfolio Kanban: Seeing the Bigger Picture, Agile Alliance experience report, 2014.
- Sandy Mamoli. Portfolio Kanban – Seeing the Bigger Picture (talk), InfoQ, 2014.
- Yuval Yeret. How to Limit and Reduce Portfolio WIP, Scrum.org, 2026.
- Yuval Yeret. What Do Busy Portfolio Kanban Boards Tell Us?, 2024.
- Nikolay Tsonev. Implementing Portfolio Kanban Tutorial, Businessmap.
- Businessmap. SCHLENK case study.
- Pavel Naydenov. Portfolio Kanban: From Team Level to C-Level Strategy, Businessmap.
- Dimitar Karaivanov. How Can Portfolio Kanban Help Your Business? (ebook), Agile Alliance, 2018.
- David J. Anderson. Enterprise Services Planning: Portfolio Management, Kanban University.
- Mike Burrows. Not "Portfolio Kanban", LKCE 2012.
- Dan Radigan. Project portfolio management with Jira Agile, Atlassian, 2013.
- Atlassian Community. Exploring Kanban as a Portfolio Overview Tool.
- Broadcom. Design a Portfolio Kanban Board, Rally TechDocs.
- Rumyana Dancheva. Portfolio Kanban: The Steel Thread from Task to Project, AgileSherpas.
- Vidas Vasiliauskas. Portfolio Kanban: Setup Guide for Multiple Projects, Teamhood, 2023.
- NimbleWork. Portfolio Kanban, 2022.
- Modus Cooperandi. Portfolio Kanban (glossary).
- Kanban Flight Levels, ProjectManagement.com, 2019.
- Berriprocess Agility. Projects, Products and Portfolio Management with Kanban (poster), DJAA.
- Chris Hefley. About WIP Limits and Card Size, Planview blog, 2011.
- IIBA. Agile Analysis Certification (AAC).
Last reviewed: October 15, 2026.